- Done this week
- Walls framed on all four sides and sheathed on the north side. Window and door openings framed.
- Inspections
- None this week. Next is the roof and wall sheathing inspection, once the roof is on.
- Next week
- Roof framing and sheathing. The plumber starts the rough-in on Thursday.
- You decide
- Where the TV goes in the living room, so the electrician can put an outlet and a cable line behind it before the walls close.
- Photos


- Payment due
- None this week. The next date is on your schedule.
Questions about any of it? Reply to this update or call your project lead.